Selective Parity Week — 2026-03-23

Context

Atlas now has a documented competitive strategy:

  • keep MVP frozen
  • preserve trust as the primary moat
  • selectively close the most visible comparison gaps against Mole, Tencent Lemon Cleaner, and Pearcleaner

This week plan turns that strategy into the next development-ready execution window.

Related docs:

Planned Window

  • 2026-03-23 to 2026-03-27

Goal

Prepare Atlas's next coding phase with a strict mainline order so development starts on the highest-pressure competitive surfaces first and does not drift into premature release work:

  • EPIC-A Apps evidence execution against Pearcleaner and Lemon
  • EPIC-B Smart Clean safe coverage expansion against Mole and Lemon
  • EPIC-C Recovery payload hardening
  • EPIC-D release readiness only after the product-path epics stabilize

Scope

Stay inside frozen MVP:

  • Overview
  • Smart Clean
  • Apps
  • History
  • Recovery
  • Permissions
  • Settings

Do not expand into:

  • Storage treemap
  • Menu Bar
  • Automation
  • duplicate-file or similar-photo cleanup as new Atlas modules
  • privacy-cleaning as a new standalone module

Sequencing Rule

Execute the next mainline epics in this order only:

  1. EPIC-A Apps Evidence Execution
  2. EPIC-B Smart Clean Safe Coverage Expansion
  3. EPIC-C Recovery Payload Hardening
  4. EPIC-D Release Readiness

Why this order:

  • the clearest competitive comparison pressure is already concentrated in Apps and Smart Clean
  • the release chain is mostly working in pre-signing form
  • public release remains blocked by missing signing materials, not by packaging mechanics

Must Deliver

  • A concrete fixture-backed baseline for EPIC-A uninstall evidence work
  • One implementation-ready plan for the first Apps evidence coding slice
  • A bounded target list for the next Smart Clean safe roots after Apps
  • Updated acceptance criteria for Apps, Smart Clean, and Recovery
  • Updated release-facing beta checklist so release work stays downstream of the product-path epics

Backlog Mapping

  • ATL-251 Define the fixture app baseline for mainstream and developer-heavy uninstall scenarios
  • ATL-252 Make Apps preview, completion, and history render the same uninstall evidence model end to end
  • ATL-253 Define the restore-triggered app-footprint refresh policy and stale-evidence behavior after recovery
  • ATL-254 Script the manual acceptance flow for uninstall evidence, restore, and post-restore refresh verification
  • ATL-256 Define the next batch of high-confidence safe roots outside app containers and freeze the no-go boundaries
  • ATL-257 Stabilize review-only vs executable boundary metadata and UI cues across scan, review, execute, completion, and history
  • ATL-261 Freeze the recovery payload schema, versioning rules, and compatibility contract
  • ATL-266 Make full-acceptance a routine gate on the candidate build instead of a one-off release exercise

Day Plan

  • Day 1
    • freeze the EPIC-A -> EPIC-D execution order
    • finalize the fixture app baseline and non-go boundaries for the first Apps slice
  • Day 2
    • define the cross-surface uninstall evidence model for preview, completion, and history
    • confirm restore-refresh expectations and acceptance criteria for Apps
  • Day 3
    • write the detailed implementation plan for the first Apps coding slice
    • identify likely file-touch map and contract-test map
  • Day 4
    • define the next Smart Clean safe roots and the review-only vs executable boundary rules
    • align roadmap, risks, and acceptance docs with the ordered epic sequence
  • Day 5
    • hold an internal doc gate for development readiness
    • confirm the next coding session can begin with EPIC-A and without another sequencing pass

Owner Tasks

  • Product Agent
    • keep parity work bounded to visible comparison pressure only
    • reject backlog inflation that does not strengthen the frozen MVP
  • UX Agent
    • define visible trust cues for supported, unsupported, and review-only actions
    • keep Atlas's UI difference legible against broader cleaner tools
  • Mac App Agent
    • identify concrete UI surfaces that must change in Smart Clean, Apps, History, and completion states
  • Core Agent
    • define the preview taxonomy and structured evidence that the UI can actually render
  • System Agent
    • define which additional safe cleanup classes are realistic next targets for Smart Clean
  • QA Agent
    • define the fixture set, comparison scenarios, and contract-style checks
  • Docs Agent
    • keep strategy, acceptance, roadmap, and release-check documents aligned

Validation Plan

Planning Validation

  • every new task maps to existing MVP surfaces
  • every new acceptance criterion is testable
  • every parity goal has an explicit competitor reference and an explicit Atlas non-goal

Readiness Validation

  • at least one implementation-ready plan exists for the next coding slice
  • acceptance matrix and beta checklist reflect the new competitive gates
  • no document implies that Atlas is reopening deferred scope

Exit Criteria

  • selective parity work is expressed as tasks, acceptance, and validation rather than just strategy prose
  • Smart Clean and Apps both have explicit competitor-driven targets
  • next coding session can start on EPIC-A without another planning pass

Known Blockers

  • signed public beta remains blocked by missing Apple release credentials
  • Smart Clean breadth still has to stay subordinate to execution honesty
  • Apps depth work must remain bounded by what Atlas can safely prove and recover
  • release readiness still cannot close the public-distribution gap until Apple signing materials exist